What plumbing certification does Tasmania require?

By Leadhand · Sources checked

In Tasmania, a plumber completes a Form 71B Standard of Work Certificate for permit or notifiable plumbing work when the work is finished, and sends it to the council permit authority with a copy to the owner. The council permit authority, not the plumber, issues the separate Form 21 Certificate of Completion. From 1 October 2026 the former CBOS functions moved to Consumer Affairs Tasmania and Building Standards Tasmania.[1][2]

Which form does what

Use the forms listed in the current Building Standards Tasmania directory, not older copies you have saved. The forms are different documents with different authors.

Which form does what
FormWhat it isWho acts
Form 3Application for permit or notifiable plumbing workGoes to the council permit authority
Form 60Start Work Notification and AuthorisationPlumber says the work is ready to start; the council authorises
Form 71BStandard of Work Certificate, Plumbing WorkPlumber completes it when permit or notifiable work is complete and sends it to the council permit authority, with a copy to the owner
Form 80Notification after completion of certain low risk (Category 2b) workSeparate from Form 71B
Form 21Certificate of Completion, Plumbing WorkIssued by the council permit authority, not the plumber

Sources[1][2]

Not every job, and timing

Form 71B applies to permit or notifiable plumbing work. Confirm the statutory timing and the council's authorisation conditions with the permit authority as part of your close-out plan, and record the due date before work finishes.

Sources[1]

Document handover checklist you can copy

This is our suggested checklist for keeping the paper trail together on each job.

Job: [address]
Permit or notifiable work? [yes / no / ask the permit authority]

[ ] Form 3 application lodged with: [council permit authority] on [DD/MM/YYYY]
[ ] Form 60 start work authorised on: [DD/MM/YYYY]
[ ] Authorisation conditions noted (including any timing): [notes]
[ ] Work completed on: [DD/MM/YYYY]
[ ] Form 71B completed by: [plumber name]
[ ] Form 71B sent to permit authority on: [DD/MM/YYYY]
[ ] Owner copy of Form 71B sent on: [DD/MM/YYYY]
[ ] Form 80 needed for low risk Category 2b work? [yes / no]
[ ] Form 21 issued by the permit authority: [date or not yet]

Sources[1][2]

Common questions

Do you get a plumbing certificate?
For permit or notifiable plumbing work in Tasmania, the plumber completes a Form 71B Standard of Work Certificate, and the council permit authority issues a separate Form 21 Certificate of Completion. Form 71B does not apply to every plumbing job.[1][2]

Official sources

Checked 16 October 2026. Rules can change; use these sources to check the requirements for your job.

  1. Tasmania: Plumbing work approved forms and their use
  2. Building Standards Tasmania: Building and trades forms
  3. Leadhand: Current product features

Related guides

Job workflows for plumbers.

Put it to work on the next job

Leadhand keeps job photos, site checklists and completed forms on the job record, so your handover documents sit with the job they belong to.

See Leadhand job records and forms