When must a WA plumber submit a compliance certificate?

By Leadhand · Sources checked

In Western Australia, major plumbing work needs a notice of intention at least 24 hours before it starts, and a certificate of compliance within five working days of completion. For emergency work, the notice and certificate can be submitted together within five working days of finishing. For minor plumbing work, keep a record for at least six years.[1][2]

Major or minor decides the paperwork

Minor plumbing work is testing, maintenance, repair or replacement of existing plumbing, such as like-for-like tap repairs. Replacing a water heater or a testable backflow prevention device is always major work. Major work also includes new fixtures, sewer conversions, and installing, altering or extending drainage plumbing.

Major or minor decides the paperwork
WorkBefore startingAfter finishing
Major plumbing workNotice of intention at least 24 hours beforeCertificate of compliance within five working days
Emergency major workNo advance noticeNotice of intention and certificate of compliance together within five working days
Work with an alternative solutionNotice of intention at least five working days before, with an extra feeCertificate of compliance within five working days
Minor plumbing workRecord the work in the Board's approved formatKeep the record for at least six years

Sources[1]

Drainage diagrams and eNotice

For major drainage work that installs, alters or extends drainage plumbing, a drainage plumbing diagram goes in with the certificate. After the notice of intention, regulation 70 requires you to notify when drainage work is completed, tested and ready for inspection, and the certificate cannot be lodged before that notification.

eNotice is free to register and use, but fixture and form fees still apply, and fees must be paid before a notice is accepted. You need your licence number and the email registered with Building and Energy. A copy goes to the customer by email if you enter their address, otherwise you give them a copy.

Sources[1][2]

Automatic Mutual Recognition plumbers

Plumbers working under Automatic Mutual Recognition have their own steps for notices and certificates. Follow the Building and Energy eNotice page for those, and do not apply the registration steps above to them.

Sources[2]

Prestart and closeout checklist you can copy

This is our suggested checklist, not a Building and Energy form.

WA PLUMBING NOTICE CHECKLIST

Job and site: [address]
Major or minor? [major / minor, why]
Emergency? [yes / no]
Notice of intention lodged: [DD/MM/YYYY, time], at least 24 hours before start [yes / no]
Alternative solution used? [yes / no, notice at least five working days before]
Fees paid: [yes / no]
Work completed on: [DD/MM/YYYY]
Drainage completed and ready for inspection notified: [DD/MM/YYYY / not drainage]
Drainage plumbing diagram attached: [yes / no / not needed]
Certificate of compliance due (5 working days): [DD/MM/YYYY]; lodged: [DD/MM/YYYY]
Copy to customer: [DD/MM/YYYY, how]
Minor work recorded: [yes / no / not minor]

Sources[1][2]

Common questions

Do I need a plumbing compliance certificate?
In Western Australia, licensed plumbing contractors need a certificate of compliance for major plumbing work, within five working days of finishing. Minor plumbing work is recorded instead.[1]
How to get a CoC plumbing certificate?
The plumbing contractor lodges it through eNotice, after registering with a licence number and the email held by Building and Energy. If you are the customer, ask the plumber for your copy, which eNotice emails to you when they enter your address.[2]

Official sources

Checked 16 October 2026. Rules can change; use these sources to check the requirements for your job.

  1. WA Government: Information for licensed plumbers
  2. WA Government: Using plumbing eNotice
  3. Leadhand: Current product features

Related guides

Job workflows for plumbers.

Put it to work on the next job

Keep job notes, photos and the invoice for each plumbing job together in Leadhand, so the dates and work details are in one place for your notices.

See Leadhand job notes and photos