For a Queensland domestic building contract, practical completion requires compliance with the contract, plans, specifications and statutory requirements, with only minor defects or omissions that will not unreasonably affect occupation. If the owner claims minor defects or omissions, the contractor must give them the defects document. Record the completion evidence, agreed and disputed minor items, remedy dates and handover documents against the job.[1][2]
What the domestic definition looks for
The Act's Schedule 1B wording for domestic building work has three parts. The work is in compliance with the contract, including all plans and specifications and all statutory requirements applying to it. It has no defects or omissions other than minor ones that will not unreasonably affect occupation. And if the owner claims there are minor defects or omissions, the contractor gives the owner a defects document.
QBCC's handover page adds that the home must be suitable for occupation, meaning it functions as a normal home, has power and water and is weatherproof. Items such as painting touch-ups can still be outstanding, but there must be no major defects. This guide covers domestic work only. Check your own contract for its definition on commercial jobs.
The defects document
QBCC says the contractor and owner walk through the property at the handover inspection and complete the defects document. It lists the minor defects and omissions both parties agree to, and must state when the contractor will attend to them. It must separately list any minor defects or omissions that only the owner believes exist. It must be signed by both parties, or, if the contractor has signed, the contractor needs to make reasonable efforts to have the owner sign.
Keep a copy of the signed document, or a record of your efforts to get the owner's signature.
Sources[2]
A practical completion record you can copy
This table is our recommended record, not a statutory form. It keeps the completion facts separate from the payment claim.
| Record | What to note | Keep |
|---|---|---|
| Scope | Contract work and approved variations completed, checked against plans and specifications | Contract, plans, specifications, variation records |
| Statutory requirements | Inspections and certificates required for the work | Certificates of inspection, final certificate where relevant |
| Occupation | Power, water and weatherproofing working | Dated photos, test notes |
| Documents handed over | Practical completion certificate for a new home, product warranties, service provider notices | Handover list signed by the owner |
| Acceptance | Date and who inspected, and who attended | Inspection notes |
| Open items | Agreed minor items, owner-only items, and when you will attend | Signed defects document |
| Payment claim | Checked separately against the contract and any certificate conditions | Claim copy and contract clause |
Notice, documents and final payment
Check the contract's notice and handover procedure before arranging the inspection. Confirm what must be delivered at practical completion and what evidence is needed for the final payment claim.
QBCC also says some contracts require all certificates of inspection, including the final certificate, before final payment, and recommends providing them before receiving final payment. A final payment request must follow the contract, plans and specifications and the statutory requirements.
Sources[2]
Record entry you can copy
Replace every square bracket, then save it on the job.
Job: [address and contract reference] Inspection date: [DD/MM/YYYY] Attended by: [names] Scope complete against contract, plans and specifications: [yes / no, notes] Statutory certificates held: [list] Power, water and weatherproofing: [confirmed / notes] Documents handed over: [list] Defects document: agreed items [number], owner-only items [number], attend by [DD/MM/YYYY] Signed by owner: [yes / no] If no, my efforts to obtain signature: [dates and method] Payment claim: checked against contract clause [number] on [DD/MM/YYYY]
Common questions
- What is included in practical completion?
- For Queensland domestic building work, the Act's wording covers work done in compliance with the contract, plans, specifications and statutory requirements, no defects other than minor ones that will not unreasonably affect occupation, and a defects document where the owner claims minor defects. QBCC adds that the home must be suitable for occupation.[1][2]
Official sources
Checked 16 October 2026. Rules can change; use these sources to check the requirements for your job.
Related guides
- How should a Queensland contractor track the defects liability period?
- How do I make a Queensland security of payment claim?
- Retention money in Queensland construction subcontracts
Job workflows for builders.
Put it to work on the next job
Leadhand lets your crew put photos, site checklists and completed sign-off forms straight onto the job, so your handover record sits with the work.
See Leadhand job photos and sign-off forms