A subcontractor's daywork docket should record who authorised the work, the site and date, the task or variation reference, the crew and hours, materials and plant, photos, any exceptions and an acknowledgement. Rates should come from the contract, quote or written variation rather than being set on the docket. A docket supports an invoice but does not replace written variation approval or the invoice itself.[1][2]
What a docket is for
A daywork docket records time and materials for work charged on that basis. Business.gov.au says contract changes can be made verbally but are best put in writing and signed, that a court can enforce an agreed variation, and that building and construction variations should be checked against state or territory rules. Treat the docket as evidence of what was done, not approval to do it.
Sources[1]
Fields to record
This layout is our recommendation, not a mandated form.
| Field | Record |
|---|---|
| Authorised by | Name and role of the person who asked for or approved the work |
| Site and date | Address, area, date |
| Reference | Task, work order or variation number |
| Crew and hours | Names, start, finish, breaks |
| Rate source | Where the rate is agreed, such as the contract clause or variation |
| Materials and plant | Item, quantity, hours on site |
| Photos and exceptions | Photos with location, plus delays, access problems or rework by others |
| Acknowledgement | Name, date and signature recording receipt |
Sources[1]
Daywork docket you can copy
Replace every square bracket. Do not put rates on the docket unless your contract says to.
DAYWORK DOCKET Docket no.: [0000] Date: [DD/MM/YYYY] Site: [address, area] Contract or order reference: [ref] Task or variation reference: [ref] Work authorised by: [name, role] on [DD/MM/YYYY] via [verbal / email / written variation] Crew and hours: [name] | [start] to [finish] | break [minutes] | [task] Work done: [description] Rates apply under: [contract clause, quote or variation reference] Materials: [item] x [qty] Plant: [item] [hours] Photos: [number and location on the job record] Exceptions: [delays, access problems, work by others, hazards] Acknowledged as received by: [name, role, date] Subcontractor: [name, date] This docket is not a variation approval or an invoice.
Sources[1]
After the docket
Match each invoice line to the docket and variation reference. Business.gov.au says a contract can specify what an invoice shows, such as the description of services and costs, so quote the docket number on the invoice. Keep dockets and photos with the job; most business records are kept for 5 years, and digital copies are acceptable.
Common questions
- What does a job sheet include?
- For daywork, a job sheet should record who authorised the work, the site and date, the task or variation reference, crew and hours, materials and plant, photos, exceptions and an acknowledgement. Rates and variation approval stay in your contract or written variation. Keep the sheet with the job to support the invoice.[1][2]
Official sources
Checked 16 October 2026. Rules can change; use these sources to check the requirements for your job.
Related guides
- What should a trade job sheet include?
- What should a building variation form include?
- What should a trade crew timesheet record?
Job workflows for builders.
Put it to work on the next job
Leadhand puts photos straight onto the job from the field app and keeps site checklists and sign-off forms on the job record.
See Leadhand job photos and forms